The Prévessin Computing Centre
Inaugurated on 23 February 2024: more than 6000 m² on the Prévessin site, six IT rooms with 2 MW of cooling each. Its PUE target of 1.1 against a world average near 1.6 is the design statement, and its heat-recovery system will warm site buildings from the winter of 2026/27. Energy is treated as an architectural constraint, not an operating expense.
Topology
- Part of: governance-structure
- Complies with: energy-objectives
- Cites: prevessin-data-centre — inauguration, dimensions, PUE.
- Cites: cern-it-environmental — energy as an IT design constraint.